Terminal News

Pelican Point Terminal Expansion Update

Written by...

Picture of Anamika Talwaria

Anamika Talwaria

Editor for Tank Storage Magazine & Chair of Women in Tanks

Three new tanks have successfully completed hydrotesting at Quantem’s Pelican Point Terminal in Australia. The tanks are now being painted, moving closer to commissioning in the coming months.

Constructed using over 1,400 tonnes of Australian steel and delivered with 165,000 site hours – without an MTI or LTI – this project showcases Quantem’s commitment to safety and quality.

The diesel expansion project includes three new tanks of 30,000 m3 storage and received grant funding from the Australian Government as part of the Boosting Australia’s Diesel Storage Program. The project remains on track to be online mid-2025.

Share this article:

Latest terminal news

Terminal News

BWC Terminals Updates Harvey Terminal

BWC Terminals has upgraded the truck rack cover at its Harvey facility in Louisiana, USA. The new structure is a more efficient hurricane-rated building, spanning the full length of the

Read More
Terminal News

Ivens Awarded Evos Malta Project

Ivens has been selected to deliver Evos Malta’s latest project. The Mediterranean terminal has a total capacity of 568,000 m3 and has been in operation since 1992. According to Ivens,

Read More