Terminal News

TGE Completes First Stage of INEOS Project One

Written by...

Picture of Anamika Talwaria

Anamika Talwaria

Editor for Tank Storage Magazine & Chair of Women in Tanks

TGE has released an update on the construction work at INEOS Project One’s Antwerp, Belgium, site.

TGE is constructing a tank roof for the 197,000 m³ ethylene tank. The tank roof will be covered by a total of 4,000 m³ of concrete. Given its vast size, TGE is applying the concrete in two equal layers – with the first layer having been successfully completed. To support the weight of the wet concrete during this phase, TGE pressurised the tank from the inside until the concrete was sturdy enough to hold its own weight.

The company says: ‘As we speak, we’re gearing up to pour the second layer, which we’ve divided into nine sections to ensure the concrete’s surface is finished to perfection. This task will span several weeks and we’re aiming to wrap it up by the early summer of 2025.’ Once the concrete dome roof is in place, TGE will move to install the top structures, including steel, piping, and electrical works.

Share this article:

Latest terminal news

Latest News

Tank Storage Magazine Launches New Podcast

Tank Storage Magazine is proud to announce the official launch of its brand-new podcast, created to inform, support and connect the global liquid bulk storage community. The first episode is

Read More
Terminal News

Neste Extends World Fuel Partnership for SAF

Neste and World Fuel Services (World Fuel) have extended their existing relationship with a five-year agreement that will expand the availability of Neste-supplied sustainable aviation fuel (SAF) at more than

Read More
Terminal News

Vopak Adds Rail Loading to Vlaardingen

Vopak has added a second dedicated rail loading and unloading system at the Vopak Terminal Vlaardingen in the Netherlands. The project included the upgrade of the existing rail station with

Read More