Coastal GasLink pipeline (TC Energy natural gas pipeline) which is under construction in British Columbia, Canada, has announced 90% completion.
Bevin Wirzba, Coastal GasLink president says: ‘It is exciting to see the tremendous progress that has been made this year. When building this extremely complex and critical infrastructure, each percentage represents a hard-fought achievement…As we reach the mid-way mark of this year, Section 6 now has 100% of pipe installed with key sections soon to follow as we work to complete the remaining 10%.’
Section 6 of the pipeline stretches 63 kms from south of Burns Lake to south of Houston, achieved 100% pipe installation in June. This followed Sections 1 and 4 which achieved this milestone last year.
Coastal GasLink continues to make important strides towards achieving project completion in December 2023.